Watch CBS News

Caltrain reducing service for 2 weeks to speed up electrification project

Caltrain installing new signal system as electrification push advances
Caltrain installing new signal system as electrification push advances 00:27

MOUNTAIN VIEW – Caltrain service will be reduced by more than one-third and end earlier each night during a two-week period beginning Monday.

Crews will be working to expedite a project between Belmont and Mountain View stations, part of a larger endeavor converting the diesel system to electric expected to be completed in 2024.

The number of trains per day will be reduced to 68 -- down from the current 104 -- on weekdays beginning Monday and last two weeks. Normal service will resume Monday, Dec. 19.

The temporary schedule is available at www.caltrain.com/december-2022-service-change.

Weekend train service between Belmont and Mountain View will be replaced by bus service. Riders can transfer to SamTrans bus service through the affected area, which will increase travel time for riders by 60-90 minutes.

The weekend bus bridges will serve all regular weekend stops between Belmont and Mountain View stations, with timed train connections via Caltrain on both ends.

During this period of construction, train service will also end early on weeknights and weekends to accelerate work being performed on the entire railroad. The last northbound train each evening will depart Tamien Station at 9:01 p.m. and the last southbound train will depart San Francisco Station at 9:22 p.m.

This construction work includes signal cutover work at 16 grade crossings, requiring a 24/7 single-tracking window between Belmont and Mountain View. 

View CBS News In
CBS News App Open
Chrome Safari Continue
Be the first to know
Get browser notifications for breaking news, live events, and exclusive reporting.