Callahan Tunnel Reopens 2 Days Ahead Of Schedule

BOSTON (CBS/AP) — The Callahan Tunnel in Boston has reopened after a $19 million makeover.

The two-lane tunnel that carries traffic from downtown to Logan Airport reopened at about 4:45 a.m. Monday, two days ahead of schedule.

WBZ NewsRadio 1030's Ban Parker reports

Callahan Tunnel Reopens

The tunnel was originally scheduled to open Wednesday, but the contractor was awarded $71,500 for each day it finished ahead of schedule.

The 52-year-old tunnel was closed for renovations on Dec. 27, creating traffic headaches for commuters and residents.

The renovation was planned after a corroded wall panel fell onto the roadway in December 2012. No one was hurt and no vehicles were struck.

The project included the replacement of the deck, curbing and wall panels.

A few minor fixes remain, but state Transportation Department officials that work will be done during the overnight hours in the coming weeks.

(TM and © Copyright 2014 CBS Radio Inc. and its relevant subsidiaries. CBS RADIO and EYE Logo TM and Copyright 2014 CBS Broadcasting Inc. Used under license. All Rights Reserved. This material may not be published, broadcast, rewritten, or redistributed. The Associated Press contributed to this report.)

MORE LOCAL NEWS FROM CBS BOSTON

View CBS News In
CBS News App Open
Chrome Safari Continue
Be the first to know
Get browser notifications for breaking news, live events, and exclusive reporting.