Natomas I-5 to I-80 connector ramps reopen nearly 12 hours early

Road construction wraps on I-80 and I-5 Sunday evening

SACRAMENTO - The 55-hour closure at the connector ramp of Interstate 5 and Interstate 80 interchange wrapped up about 12 hours early and ahead of the Monday morning commute.

Caltrans had planned for the interchange to reopen by Monday at 5 a.m., but CBS13 saw traffic moving through the area that was closed around 5 p.m. Sunday. 

Southbound I-5 to eastbound and westbound I-80 was closed Friday night at 10 p.m., as well as eastbound I-80 to northbound I-5.

Many drivers had to use a detour throughout Veterans Day weekend, using Truxel Road from eastbound I-80 to northbound I-5, and Garden Highway from southbound I-5 to I-80. 

Crews did slab work, hauling and pouring concrete, as well as stripping the road.

Read more
f

We and our partners use cookies to understand how you use our site, improve your experience and serve you personalized content and advertising. Read about how we use cookies in our cookie policy and how you can control them by clicking Manage Settings. By continuing to use this site, you accept these cookies.