Feds Seek $11K Fine For Fire That Closed Liberty Bridge

PITTSBURGH (AP) - The federal Occupational Health and Safety Administration wants to fine a contractor $11,224 for a construction fire that wholly or partially shut down the Liberty Bridge for 24 days.

Contractor Joseph B. Fay Co. didn't immediately comment Wednesday. The company has 15 days to appeal.

The Pennsylvania Department of Transportation has already said it wants Fay to forfeit more than $3 million of the $80 million the company is owed for the Liberty Bridge reconstruction project.

PennDOT and OSHA both say hot residue from a blowtorch ignited plastic piping and a construction tarp on Sept. 2. The fire's heat bent a 30-foot steel support beam that needed to be repaired before the reconstruction could continue.

Fay has said it largely made up for construction delays and is hoping to reduce the PennDOT penalty.

Join The Conversation On The KDKA Facebook Page
Stay Up To Date, Follow KDKA On Twitter

(© Copyright 2017 The Associated Press. All Rights Reserved. This material may not be published, broadcast, rewritten or redistributed.)

Read more
f

We and our partners use cookies to understand how you use our site, improve your experience and serve you personalized content and advertising. Read about how we use cookies in our cookie policy and how you can control them by clicking Manage Settings. By continuing to use this site, you accept these cookies.