City Council Approves Skyscraper Near Grand Central In Exchange For Transit Hub Work
NEW YORK (CBSNewYork/AP) -- City officials cleared the way Wednesday for construction of a new, 65-story Manhattan skyscraper after the developer made an unusual tradeoff: a promise to make sweeping upgrades to nearby Grand Central Terminal that would allow more rush-hour trains on the subway's busiest lines.
New York City Council members unanimously approved a change to zoning law that will allow One Vanderbilt to rise alongside the historic transit hub. In exchange for getting more square footage, developer SL Green Realty Corp. will invest about $220 million in critical improvements to Grand Central, allowing more trains to run during rush hour on the clogged 4-5-6 lines, which carry more people per day than the entire transit systems of Chicago or Washington, D.C.
"This is the first time we've seen vast private investment to improve mass transit access," said Mitchell Moss, a professor of urban planning at New York University.
The partnership could be a prototype for the future, allowing the debt-burdened Metropolitan Transportation Authority, which runs the city's subway system and commuter rails, to offload the cost of improving its aging infrastructure onto private developers. And it will transform the stodgy East Midtown area, where the average building is 75 years old and saddled with outdated structural features such as interior columns and low ceilings.
Anchored by tenant TD Bank, the building is expected to house about 8,000 workers when fully occupied. It will join a parade of new skyscrapers -- many of them in the west 50s near Central Park, including the Nordstrom Tower on 57th Street -- that will soon soar above Midtown Manhattan and irrevocably alter the skyline.
The tower will house a gleaming new transit hall that will funnel workers directly into Grand Central and also provide a crucial direct link from commuter trains to the subway system for the MTA's East Side Access project, which will bring 65,000 Long Island Rail Road commuters directly into the terminal when it opens in about seven years.
The most important work will happen on the 4-5-6 platform, one of the most notoriously overcrowded waiting areas in the subway system. During rush hour, commuters often have to watch several trains pass before they are able to squeeze onto one. The main problem is lack of space on the platform itself, which is dominated by numerous thick columns that take up unnecessary space, transit officials say.
"This is the bottleneck to the subway line," Edith Hsu-Chen, director of the Manhattan office of the city's department of planning, told city council members during a hearing last month. "Improvements made to this station would affect the entire line and commuters in the whole city."
SL Green will strip the columns down to the bare bones -- slimming them down by about a foot each -- and narrow the stairwell to create about two and a half feet of extra space on the platform. That may not sound like much, but on a crowded platform, it could make a world of difference.
"As a result, we expect that the trains will move faster," City Councilman Dan Garodnick, D-Manhattan, told WCBS 880's Rich Lamb. "We're actually going to get one additional train per hour through during the rush hour. That's a big deal."
"At rush hour, people congregate around these columns. People can't get off the train," added Robert Schiffer, managing director at SL Green. "The idea is to diffuse people."
All improvements will be complete by 2020 or 2021, about two or three years before the East Side Access project will be finished, Schiffer said.
(TM and © Copyright 2015 CBS Radio Inc. and its relevant subsidiaries. CBS RADIO and EYE Logo TM and Copyright 2015 CBS Broadcasting Inc. Used under license. All Rights Reserved. This material may not be published, broadcast, rewritten, or redistributed. The Associated Press contributed to this report.)