Red Wing Bridge Crews Work Around The Clock To Finish Before Rise Of Miss. River

MINNEAPOLIS (WCCO) -- Construction crews are working 24 hours a day to complete the Red Wing Bridge before Mississippi River levels rise.

According to the Minnesota Department of Transportation, crews building the new Highway 63/Eisenhower Bridge in Red Wing are working 24 hours a day to set tub girders.

The project contractor, Zenith Tech, Inc., are setting tub girders for pier 2, which is the Mississippi River navigation channel, and pier 3 on the Wisconsin side. Work shifts are planned Monday through Friday, but weekend work could be added depending on progress and weather.

The work is not expected to affect Highway 63 traffic using the river bridge.

Read more
f

We and our partners use cookies to understand how you use our site, improve your experience and serve you personalized content and advertising. Read about how we use cookies in our cookie policy and how you can control them by clicking Manage Settings. By continuing to use this site, you accept these cookies.