Some Detroit People Mover stations to close for system upgrades

Some Detroit People Mover stations to close for system upgrades

DETROIT, Mich. (CBS DETROIT) - The Detroit Transportation Corporation (DTC) released a schedule for the next round of station upgrades. 

Starting Jan. 15, two stations will be closed to the public each week for five-day installations. New surveillance cameras and PA equipment are set to be installed. 

The project is scheduled to continue through March 1 as scheduled:

  • Jan. 15-19: West Riverfront & Grand Circus Park
  • Jan. 22-26: Huntington Place & Millender Center
  • Jan. 29-Feb. 2: Michigan & Bricktown
  • Feb. 5-9: Cadillac & Times Square
  • Feb. 12-18: Greektown & Financial District
  • Feb. 19-23: Broadway & East Side Substation
  • Feb. 26-Mar. 1: Fort/Cass & Renaissance Center  

People Mover trains will bypass the closed stations, officials said. Residents are asked to temporarily use the nearest and next available People Mover station to complete their trips. For a map of station stops, visit the website.

Read more
f

We and our partners use cookies to understand how you use our site, improve your experience and serve you personalized content and advertising. Read about how we use cookies in our cookie policy and how you can control them by clicking Manage Settings. By continuing to use this site, you accept these cookies.