I-25 Widening Project In Douglas County Expected To Be Completed Several Months Early

DOUGLAS COUNTY, Colo. (CBS4) - The Colorado Department of Transportation has announced more nighttime closures of Interstate 25 lanes and ramps in Douglas County as Phase 2 of the widening project is scheduled to be completed at the end of April.

CDOT is adding one lane in each direction between County Line Road and Lincoln Avenue. Phase 2 widens the east side of I-25.

"Paving operations require full closure of the eastbound Lincoln Avenue on-ramp," CDOT said in a statement.

This weekend, beginning Friday at 9 a.m., the eastbound Lincoln Avenue loop on-ramp to northbound I-25 will be closed until Monday at 5:30 a.m. The ramp will also be closed overnight on Wednesday from 10 p.m. to Thursday at 5 a.m.

"Together, the overnight and weekend closures save weeks of inconvenience and traffic impacts associated with partial ramp closures and phased paving operations," CDOT said.

The $32 million project wasn't expected to be finished until 2016.

"CDOT now anticipates that the entire I-25 project will be substantially complete by the end of 2015 – several months early."

LINK: Traffic Section

Additional Information From CDOT

Updated information regarding traffic impacts on this project is available by calling the project hotline (303) 358-7643 or visiting the website at www.coloradodot.info/projects/i25lanebalance. For information on other projects, visit http://www.cotrip.org/roadConditions.htm, call 511 or downloading CDOT mobile. To receive project updates via e-mail, visit www.coloradodot.info and click on the cell-phone icon in the upper right-hand corner.

Read more
f

We and our partners use cookies to understand how you use our site, improve your experience and serve you personalized content and advertising. Read about how we use cookies in our cookie policy and how you can control them by clicking Manage Settings. By continuing to use this site, you accept these cookies.