Port of Baltimore reopens Wednesday after $100M cleanup of collapsed Key Bridge

Port of Baltimore reopens Wednesday after $100M cleanup of collapsed Key Bridge

BALTIMORE (CBS/AP) -- Authorities anticipate commercial shipping traffic through the Port of Baltimore will soon return to normal levels since the channel fully reopened earlier this week for the first time since the Francis Scott Key Bridge collapse.

"They are back open for business, ready to bring in the largest container ships that call there," U.S. Coast Guard Rear Admiral Shannon Gilreath said during a virtual press briefing Tuesday afternoon.

Some shipping companies rerouted their cargo to other ports following the deadly bridge collapse in March. The disaster halted most maritime traffic through Baltimore's busy port as crews worked around the clock to clear an estimated 50,000 tons of fallen steel and concrete from the Patapsco River — a roughly $100 million effort that involved federal, state and local agencies, officials said.

Maryland will announce the full reopening of the Port of Baltimore on Wednesday, according to the White House

Companies expected to return to Baltimore 

Companies that steered clear of Baltimore during the cleanup efforts will likely come back now that the channel has been returned to its original depth and width, officials said. The city's port processes more cars and farm equipment than any other in the country.

All that rerouted commercial traffic "belongs in Baltimore today," U.S. Transportation Secretary Pete Buttigieg said. "We have every indication that that is what is taking place, but we will be reinforcing that expectation as we speak with players up and down the supply chains."

The cost of the Key Bridge disaster

Crews were able to reopen portions of the deep-draft channel in phases, restoring some commercial traffic in recent weeks. Some cruise ships and large container ships have already passed through, officials said.

But thousands of longshoremen, truckers and small business owners have seen their jobs impacted by the collapse and its economic ripple effects, which extend well beyond the Baltimore region.

Officials estimated the salvage operations will cost up to $75 million, while the Coast Guard response has cost $24 million to date.

Rebuilding the bridge could cost nearly $2 billion, officials have said. They hope it's completed by 2028.

The Biden administration approved $60 million in immediate federal aid, which Buttigieg referred to as "a down payment on the work ahead." All of that aid has been committed, said White House Deputy Chief of Staff Natalie Quillian.

President Joe Biden has pledged that the federal government will cover the full cost of rebuilding the bridge, though officials said the funding is still awaiting approval from Congress.

In a statement Tuesday, Biden praised the work of everyone involved in the recovery effort to date.

"Baltimore can count on us to stick with them every step of the way, and we will continue to have your back until the bridge is rebuilt," he said.

Plans set for rebuild 

The Maryland Transportation Authority confirmed on Tuesday that no design decision has been made for a rebuilt bridge.

"While the exact nature of the approach for the bridge is still under development, we strive for a new bridge that will accommodate the needs of the port and provide enhanced protection for the new bridge pier foundation," Brian Wolfe, the Director of Project Development at MDTA, said. "We anticipate a bridge that will be built largely in the same location, staying within existing MDTA property, and will provide a four-lane roadway."

The MDTA set the following Key Bridge rebuild milestone dates: 

  • Proposals are due by Monday, June 24, 2024
  • Project team selection by mid-to-late summer 2024 
  • Project completion by Fall 2028

Construction may be able to commence in the mid-2025 timeframe after the design is "substantially developed," Wolfe said. 

11 weeks ago, a tragedy

The cargo ship Dali crashed into a critical support column of the Francis Scott Key Bridge in the early hours of March 26, collapsing the span and sending six members of a roadwork crew plunging to their deaths

The ship had lost power shortly after leaving Baltimore for Sri Lanka. A National Transportation Safety Board investigation found it experienced power outages before starting its voyage, but the exact causes of the electrical issues have yet to be determined. The FBI is also conducting a criminal investigation into the circumstances leading up to the collapse.

The Dali remained stuck amid the wreckage for almost two months, with a massive steel truss draped across its damaged bow. On May 20, the ship was refloated and guided back to port. That allowed officials to open a channel that was 50 feet (15 meters) deep and 400 feet (122 meters) wide, big enough for most of the largest commercial vessels.

The full federal shipping channel is 700 feet (213 meters) wide. Officials said two-way traffic can resume now that it has reopened. They said additional safety requirements have also been lifted because of the increased width.

Read more
f

We and our partners use cookies to understand how you use our site, improve your experience and serve you personalized content and advertising. Read about how we use cookies in our cookie policy and how you can control them by clicking Manage Settings. By continuing to use this site, you accept these cookies.